Support our Nation today - please donate here
News

£377m spent saving blast furnaces months after Port Talbot closure

16 Mar 2026 3 minute read
A steel worker at one of the blast furnaces at the British Steel site in Scunthorpe, Lincolnshire. Photo Darren Staples/PA Wire

The UK Government spent £377 million to prevent the closure of the country’s last remaining blast furnaces at British Steel’s Scunthorpe plant, according to a new report.

The emergency intervention came less than a year after the shutdown of the final coal-fired blast furnace at Port Talbot, which ended more than a century of primary steelmaking at the UK’s largest steelworks.

A report by the National Audit Office (NAO) said the Department for Business and Trade (DBT) stepped in quickly in 2025 to keep the Scunthorpe furnaces operating, warning that their closure would have led to thousands of job losses and major disruption to key supply chains.

The £377 million spent between April 2025 and January 2026 has been classified as a loan, but the NAO warned that total costs could exceed £1.5 billion by 2028 if current spending levels continue.

Operating the furnaces is currently costing around £1.3 million a day, the report said, with no fixed budget, repayment schedule or clear end date for the government support.

British Steel’s owner Jingye had been in talks with the Government between 2022 and 2025 about switching the plant to electric arc furnaces, but no agreement was reached.

In March 2025 the company said it was losing around £700,000 a day due to difficult market conditions, tariffs and environmental costs and warned that it was considering closing the blast furnaces.

The NAO said this would have resulted in major job losses in Scunthorpe and would have affected key customers including Network Rail and other infrastructure projects.

Emergency legislation was passed allowing the Government to instruct the company to keep the furnaces operating while officials moved quickly to secure raw materials and maintain production.

Alongside the £377 million used to keep the plant running, £15 million has been spent on advisers and £359 million paid to British Steel to cover operational costs including raw materials, wages and other expenses.

The NAO estimates spending could reach £615 million by June and, if maintained at current levels, could exceed £1.5 billion by 2028.

It also said the Department for Business and Trade has not yet set out a repayment schedule and it remains unclear whether the company will be able to repay the loan.

Serious economic damage

Gareth Davies, head of the NAO, said the department acted quickly to prevent serious economic damage.

“DBT was able to act quickly to save British Steel’s Scunthorpe furnaces from closure, avoiding heavy job losses and serious impacts on major UK infrastructure and construction projects,” he said.

“However, the trade-off is the significant cost of maintaining operations, and uncertainty over how long this will continue.”

The intervention stands in contrast to developments at Tata Steel’s Port Talbot works, where the UK Government committed £500 million to support a transition to lower-emission electric arc furnaces after Tata warned it was losing around £1 million a day.

The closure of the blast furnaces at Port Talbot resulted in 2,800 job losses, with thousands more roles across the wider supply chain expected to be affected.

Alasdair McDiarmid, assistant general secretary of the Community union, said the Government had taken the right decision to support steelmaking.

“The Labour Government took decisive action to secure the blast furnaces at Scunthorpe, saving thousands of jobs in the process,” he said.

“Should the Government have sat on its hands and allowed British Steel to collapse, the financial and social impacts would have been catastrophic.”


Support our Nation today

For the price of a cup of coffee a month you can help us create an independent, not-for-profit, national news service for the people of Wales, by the people of Wales.

Subscribe
Notify of
guest

5 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments
Undecided
Undecided
32 minutes ago

And circa £80m at Port Talbot without a serious effort to save the furnaces. Tells us everything we need to know about UK government priorities.

Alwyn
Alwyn
18 minutes ago
Reply to  Undecided

It’s comparing different scenarios.
Both Tata and Jingye/BS had no choice to move away from blast furnace production due to new import regulations into the EU.
Obviously, the change was easier for tata as they have a european manufacturing site to manage the transition more seaminglessly

Last edited 17 minutes ago by Alwyn
Stan
Stan
7 minutes ago
Reply to  Alwyn

So, Brexit.

Gary225
Gary225
3 minutes ago
Reply to  Alwyn

Possibly so, but there is another difference. China is an investor to encourage and avoid annoying. Tata is an Indian company, and the Raj mentality prevails in dealings with India….and Wales of course.

Stan
Stan
2 minutes ago

If Whitehall doesn’t support the north of England it might one day rise up against them. If Whitehall doesn’t support Wales it’ll be further impoverished making the north of England feel better about the south hoarding the wealth and opportunity and less likely to rise up against Whitehall.

Our Supporters

All information provided to Nation.Cymru will be handled sensitively and within the boundaries of the Data Protection Act 2018.