Is it too late to save the Welsh countryside from electricity pylons?
Jonathan Dean, Director of The Campaign for the Protection of Rural Wales
The long speculated north south pylon line seems to be on.
Identified as critical to the U.K. government’s aim for clean power by 2030, necessary to get electricity from Scotland to south Wales and facilitating the mass building of onshore wind farms in mid Wales, National Grid are now offering connection agreements to it
How did we get here and where will it go?
The transmission grid in Wales
The electricity transmission system in Wales exists only in the north and the south. It’s more correct to say that some parts of the GB grid are in Wales, than to talk of a Welsh grid, as strictly speaking there is no Welsh grid, just some parts of the GB grid are in Wales
In the north, from the site of the decommissioned Wylfa nuclear power station a 400 kV line runs to Pentir near Bangor. From here it goes two ways – along the coast via Bodelwyddan to Connah’s Quay and through Eryri, via Trawsfynydd to Wrexham. Connah’s Quay and Wrexham link in with lines in England
In the south, from Pembroke power station, two lines run to Swansea North substation, where they go two ways – along the head of the valleys eventually to Walham substation in Gloucester and along to foot of the valleys eventually to Melksham substation east of Bath.
These two are linked by Cilfynydd substation north west of Caerphilly
These two parts of the grid are connected to each other by a route around Birmingham and the midlands, and ultimately all other parts of GB.
There are no transmission lines linking the two parts more directly through mid Wales – mainly because electricity demand there is so low, there is little generation, and they are not needed. But all that is about to change, the north will be connected to the south
Linking north to south
There have been tentative ideas to connect the transmission grid in north Wales to that in the south since at least 2009. Then the idea was a subsea connection from a new nuclear station at Wylfa to Pembroke.
Also, back in 2012 National Grid Electricity Transmission (NGET) wanted to build a 400 kV transmission line from Lower Frankton in Shropshire to Cefn Coch, north west of Newtown, to service mid Wales wind farms. Neither of these happened when the generation projects were cancelled.
In 2020 the Offshore Transmission Network Review (OTNR) again suggested a subsea connection linking Lancashire to Wylfa to Pembroke, taking in new Irish Sea wind farms along the way
Offshore transmission has many plus points. It avoids every single wind farm having to send a cable to shore (termed radial connections) digging cable trenches each time, it avoids having substations in open countryside on agricultural land, as the cables only have to come ashore once, closest to where the electricity is needed, it needs less infrastructure overall and according to Ofgem will cost less
Linking north to south Wales also has merits, as it allows power from the Irish Sea to feed the south, or the Celtic Sea to feed the north. Mid Wales can always get sufficient power via the north and south distribution systems
But what about getting electricity from Scotland to England?
Scotland has vast resources for wind power. It can generate 2-3 times what it needs to reach net zero. Wales too could generate 150% of 2050 demand just from offshore wind.
England though is deficient in renewables, so subsea cables are planned down the North Sea on the east coast and Irish Sea on the west coast. There is already a cable from Scotland into Deeside, and there is no reason why others could not come into Pembroke where the grid currently has lots of spare capacity to get power into England
However, the Holistic Network Design (HND) of 2022 didn’t do this. It brought power subsea from Scotland into Pentir (near Bangor) and took power from Pentir to Swansea North substation.
Although heavily caveated as just indicating a network need, and not indicating a technology or route, it was described as a “double circuit” which basically means pylons, and Ofgem approved the pre-construction funding
In the “Beyond 2030” report earlier this year the National Energy System Operator (NESO) doubled the capacity of that in the HND, but interestingly showed the extra capacity connecting to Bodelwyddan not Pentir.
NESO have since confirmed they are considering either, or both, landing points
Why the switch from offshore to onshore?
Although Wales can easily generate sufficient energy to reach net zero, and send an extra 50% to other parts of GB, from only offshore wind, there is a problem – Wales isn’t “allowed” to make decisions about the Welsh sea, only Westminster can do that.
The previous U.K. government prioritised the North Sea, while the current U.K. government is still mulling things over. This left the Welsh government with onshore wind as the only option. Depending on how you view the Welsh Government they were either forced by an unresponsive Westminster or just don’t care about the Welsh countryside.
Either way, the Welsh countryside is certainly “open for business” as far as onshore wind development goes
But there has always been a problem, the lack of a “collection” system to funnel all that energy to market.
The wires on poles sufficient to get enough power in just aren’t sufficient to get power out. The need to connect Scotland to the south Wales grid was too good an opportunity to miss.
Route those pylons through the middle of Wales and every other hill can have a wind farm, as there is an unending “thirst” for power in south east England (pun intended)
Mid Wales still doesn’t need any of this infrastructure, even though they are going to get it. The NESO projections for 2050 show mid Wales needs little more than a few 132 kV circuits on wooden poles to provide everything they need for net zero.
What all of rural Wales needs is the distribution system upgrading – the wires on poles that get electricity to homes and businesses at lower voltages, but currently very little is being done about this.
People in places like Builth Wells will be faced with the perverse situation of having wind farms and transmission lines but still not being able to get enough electricity for a heat pump or EV at home.
Unfortunately this level of detail isn’t exciting enough for politicians and transmission, over which the Welsh government have no control, is frequently confused with distribution, over which the Welsh Government has some control
Where will the north south line go?
National Grid are still claiming that the north south project is “early days” and they are still considering all options, but there are facts emerging:
Bodelwyddan is fast becoming an energy hub with numerous offshore wind farms coming ashore there, as well as solar and storage projects and an interconnector to Ireland.
A substation is planned at Gwyddelwern, near Corwen, for a number of onshore wind farms to the west near Bala (some right up to the boundary of Eryri national park) and battery storage (BESS).
The Mynydd Mawr proposed wind farm at Llanrhaeadr ym Mochnant to the west of Oswestry has been offered a connection agreement to the north south line (possibly at Gwyddelwern). Scottish Power still have a project, started in 2011 but put on hold, for a substation at Cefn Coch near Llanfair Caereinion to the north of Newtown for several wind farms.
The Carnedd Wen proposed wind farm near Mallwyd to the east of Dolgellau will connect to a substation called Mid Wales West but neither National Grid or Scottish Power will say where this is.
The adjacent Esgair Ddu proposed windfarm (also up to the boundary of Eryri national park) doesn’t appear to have a connection agreement yet but will likely use Mid Wales West.
Lightsource have a wind/solar/storage project called Berthlwyd that will connect to a substation called Mid Wales Connection Node A, but both the project and substation location is not clear.
Swansea North substation is said to have no spare capacity and is spatially constrained by solar parks so cannot expand.
A substation is planned at Llandyfaelog, south of Carmarthen, for several mid Wales wind farms as well as the Celtic Sea wind farms. This has had several names including Ferryside and Pont Abraham but is now known as South Wales West Connection Node C.
In addition, the routing of overhead transmission lines has to be according to the Holford Rules contained in National Policy Statement EN-5 which includes:
Avoiding national parks and other designated landscapes – this would make Pentir a difficult starting point but cause no problems for Bodelwyddan
Using the most direct route possible
Using valleys as “transmission corridors” where pylons are not seen against skylines
Piecing all this together, a possible route for the line to take is; starting at Bodelwyddan head south down the Vale of Clwyd, Gwyddelwern, Cefn Coch, once near Builth Wells head south west down Dyffryn Tywi to Llandyfaelog.
Bingo! The north is connected to the south
No doubt National Grid are busy offering connection agreements to the line so that when there is the eventual public outcry they can claim to be contractually bound to provide it
Personal thoughts and feelings
I have long been an advocate for renewables but also the right infrastructure in the right place. Routing pylons, yesterday’s technology to solve tomorrow’s problems, through the Welsh countryside, where there has never been such industrial structures, feels instinctively wrong, although I’m sure many of National Grid’s engineers are very excited.
If there wasn’t the misguided desire to extract wind power from inner Wales, the alternative could be far simpler and elegant, a subsea HVDC “bootstrap” linking Pentir to Pembroke, as was proposed fifteen years ago.
We can achieve net zero using only offshore wind. The Irish Sea alone can produce more energy than the whole of onshore Wales. We can transmit the energy long distances under the sea. We can get the energy to even the remotest farm using wooden poles or “ploughed in” cables. We can protect and conserve our landscapes for future generations. Everything is possible, but we’re not doing it.
Instead we are littering our hills and moorlands with industrial wind farms, and stringing them all together using 55 m high steel lattice pylons. North Wales will literally be surrounded by a “ring of steel”
More offshore wind farms will come, in time, as will the subsea cables, as the U.K. needs the energy, but it’ll be too late to save the Welsh countryside. It makes me sad, angry but most of all betrayed, as the promise of new technology is once again being missed.
Support our Nation today
For the price of a cup of coffee a month you can help us create an independent, not-for-profit, national news service for the people of Wales, by the people of Wales.
Such industrialisation and destruction of the Welsh countryside is criminal
This situation can be seen for what it is by thinking of it as electricity’s equivalent of Tryweryn.
Actually it’s the opposite. Currently large amounts of green power get exported from North Wales to England whilst South Wales has the dirtiest grid power in the whole UK (92% gas powered currently) and there is no link between N and S Wales. Completely needed, especially if we have aspirations of independence in the future.
Grid power HAS to provide energy ‘on demand’. You’re never going to get energy independence from an intermittent source.
Pembroke power station is looking at carbon capture or hydrogen I believe
We’ve been “looking at” CCS and hydrogen for 20 years. It’s just a climate delay tactic by the fossil fuel industry. Don’t take it seriously.
I know, but we have also been pumping CO2 into oil reservoirs to force more oil out. The issue is more cost rather than technical possibility. Again, hydrogen is perfectly possible, but the cost is the issue, and we don’t need it just yet
Yes you are. You just work out a cost effective way of storing the excess energy. Batteries will probably be the way to do this, but you can do it with high up water or even by superheating sand in a silo.
It’s exactly the same as how we’ve had a reliable water supply for the last 100+ years in this country despite the fact that it doesn’t always rain.
Batteries are fine for short term intra day storage but not inter season. Hydrogen from wind seems to be the favourite but not demonstrated at scale yet
Why not? Why would a battery work one day and not the next?
I really don’t buy into all this pylon panic. I grew up in south Manchester where town merged into country and lines of pylons were, in my young days way back in the late ’50s, an established feature of our local countryside. For me, maybe because I’d never seen anything different, heir impact was pretty minimal and they even had a certain elegant grace. Given the grim realities of climate change, lines of pylons traversing the countryside seem a small price to pay for a more energy-secure and climate-friendly future. Give the moaning a rest!
It has nothing to do with not addressing climate change. A north south offshore bootstrap would connect north to south and offshore wind can get Wales to net zero one and a half times over. Community scale schemes, using the distribution grid, can engage people in the journey to net zero. Schemes like this drive people into the open arms of climate change deniers which will slow down achieving net zero
How much more would undersea interconnectors cost than on land pylons, and how are they maintained?
The Western Link from Scotland to Deeside used subsea HVDC as it was cheaper than coming overland with pylons
Interesting. You do lose the ability to directly power the communities it goes through though. And you still need pylons at the shoreline. Also still unsure how you maintain them.
So little electricity is used in mid Wales, and it’ll still be low in 2050, the communities can be powered with the existing “wires on poles”
I don’t know how they are maintained myself, but we have interconnectors with France, Belgium, Netherlands, Germany, Denmark, Norway and Ireland, and every offshore wind farm has a cable to shore, so it’s pretty established technology
I believe these pylons will be much taller. Also, they will cut up already threatened farmland with access roads and concrete. Plus, they will be built from imported materials which will have to be transported. Plus, there is no provision for decommissioning turbines or pylons when they come to the end of their useful life. Shall I stop now?
Betrayed, sold down the river, taken for mugs…and all the while our betters in the bay rub their hands at the thought of all that filthy lucre…
Well, it’s not like we didn’t know Labour would do this is it? Yet we voted for them.
If a rail link were re-instigated between Bangor and Carmarthen would it not be possible to lay an underground electricity transmission cable at the same time as the rail infrastructure? (maybe a nice inter-community cycleway too, doubling as maintenance access?)
Not at the capacity of those cables they need cooling.
Cooling!…via heat exchanger into community use…
National Grid actually use heat recovered from transformers to heat offices at one of their substations
Put them underground.
More robust. Use old / disused gas mains etc
You can undergound the local distribution cables easily it gets more complicated for the larger cables https://www.nationalgrid.com/sites/default/files/documents/39111-Undergrounding_high_voltage_electricity_transmission_lines_The_technical_issues_INT.pdf
This report is nearly ten years old. Things have moved on since then. Countries like Denmark have abandoned pylons for undergrounding.
Thought that was the lower voltage 130-150KV lines not the 400KV lines?
HVDC (High Voltage Direct Current) is cost effective since it is more efficient at tranporting energy over distance. It is why the connector with Norway across the North Sea is HVDC.
So who exactly are making these decisions – sounds like National Grid which is a commercial company. The Welsh Government has no input, so which part of Westminster is pulling the strings? This does not appear to be a party issue as this has been pushed for the last 4 years.
So the overland cable route will either have to go through Eryri National Park or the new proposed Clwyd/Berwyn National Park which will share a boundary around the Berwyn Mountains?