Our broken planning system for renewable energy developments

Grace Lloyd, local democracy reporter
Every time an application for a large wind farm or solar farm is submitted to the Welsh Planning Department (PEDW), a long and complicated process is kicked off.
Many Welsh government bodies and other official organisations have to be consulted for each application. The organisations consulted typically include the local council – planning experts, ecologists, highways experts. Then engagement is required with additional organisations – Natural Resources Wales, NATS (National Air Traffic), CADW. Fire and Rescue services, the Health and Safety Executive, MOD and more.
Individuals from each of these organisations are required to read the wind or solar farm developer’s application – usually hundreds of pages long. Then they have to report back to PEDW with their findings and expert opinions.
It is frequently a tactic of renewable energy developers to plan a very large industrial renewable energy park and then split it down into multiple smaller developments – at least on paper.
Multiple applications
Each of these smaller developments is designed to link together with the others and share grid connections and roads, forming a huge energy park. However, they are submitted as multiple applications.
The reason developers break down their applications like this is to make these smaller developments look more friendly, with less impact to the local views, biodiversity, habitats and the communities they are going to impact. The extra effort in creating all this paperwork benefits the developers. A single smaller, less intrusive development is more likely to gain the consent of PEDW, than a huge industrial park.
Now think of all the people that were involved in the single application, outlined above, and multiply that number by 3, 4 or even 5 times, as this is how many smaller applications may be created by splitting up a large renewable energy park. So now, multiple reports are required for each of the smaller applications, often from the same individuals from the council, Natural Resources Wales, NATS and so on.
These public servants are spending months of their time working on multiple applications from renewable energy developers in Wales, when they should really be working on one single large application. And while they are doing this, they are kept from doing their day jobs of helping to run the country.
Inefficient
This is ridiculously inefficient and a dreadful waste of public money. Large renewable energy projects fall into the category of Developments of National Significance (DNS). Where DNS renewable energy applications are adjacent to each other, and intend to share grid connections, roads, or other infrastructure, it is surely obvious that they should be submitted as the single development they really are. This would save Welsh Government a huge amount of money in admin costs. It would also mean that proper environmental assessments could be carried out, covering the whole area to be built on as a single habitat, not just in pockets.
Timing is also an issue. Not only are DNS applications often submitted for multiple, smaller developments, when they could just be issued for one. They are also often issued concurrently, so a small area will have two or three active applications in progress at the same time.
For example, over Christmas and New Year 2024-25, in one small area, two applications were launched a week apart. One was for a solar farm and the other for a wind farm on Mynydd Maen, between Newbridge and Cwmbran. The consultees (that big list of government personnel, and more) had around 6 weeks to read two sets of documentation and write their reports – all over Christmas and New Year.
Next, over Easter 2025, a further consultation was launched for a third wind farm connecting to the previous developments, in the same small area. Meanwhile, further information was released regarding the first wind farm (remember the Christmas application?). Both of these required large amounts of technical information to be read and reported on again, over the Easter and Early Spring bank holidays. There are more examples, but you get the picture.
Planning law says that the public must be given an opportunity to engage with planning applications and be able to comment on what is happening in their back yard. Communities are invited to read the application documents and respond at the same time as the government representatives. However, the sheer volume of information and the timing of the applications – especially when they have been launched concurrently and over holiday periods – make it virtually impossible for any ordinary citizen to keep up with.
Public consultations
When public bodies launch public consultations, they are required to abide by the Gunning Principles. This is a set of 4 guidelines to ensure good practice and fairness. Gunning Principle 3 says that people must have “adequate time for consideration and response”. This seems impossible to achieve when multiple applications are appearing concurrently. Effectively a five-week period is reduced to two and a half weeks, when there are two applications to read and respond to within the same period. This is certainly not in line with the spirit of the Gunning Principles.
It would be much fairer to the public, and this may also extend to government employees and public servants, if there were a rule in place saying something to the effect of:
“Where developments are within 10km distance from each other, the application process must be timed to avoid communities being required to engage with more than one at any single time. That is, one application must be completed before any other is put out to public consultation, within that 10km area.”
Senedd elections
Something needs to change, and with the Senedd elections in May 2026, things seem likely to change, looking at the opinion polls in Wales.
The current DNS process has been relentlessly pounding many Welsh communities with a continuous stream of planning applications for renewable energy developments. People are simply exhausted.
Communities in the firing line for these multiple developments feel overwhelmed. Many are on the lookout for an alternative government that will make this stop. Perhaps this would be a climate-change denying political party that would stop all renewable energy developments if elected.
In my personal opinion, this would be a shame. We need to find less damaging means of producing renewable energy that benefit Welsh communities without destroying their landscapes and heritage. Welsh Government should take heed and at least address our broken planning system while there is still time.
Support our Nation today
For the price of a cup of coffee a month you can help us create an independent, not-for-profit, national news service for the people of Wales, by the people of Wales.


Trydan Gwyrdd Cymru and all the Wind Turbine huggers are deluded if they think little Wales can halt global climate change. It’s their fantasy. In the real world its profiteering.
See example Grid for India below – how can little Wales offset all this carbon?
https://iced.niti.gov.in/energy
“Little Wales” has no intention of trying to offset the carbon of India. As I’m sure you already know, each country is responsible for its own carbon emissions and has its own timelines. Telling India how to run their own affairs probably won’t go down too well However, both Wales and Scotland do seem to be trying to, at least partially, offset the carbon of England. Both Wales and Scotland are aiming to produce considerably more electricity than they will ever consume. Both nations could easily support themselves only by using offshore wind (the most popular form of generation with… Read more »
China is way ahead in green, their wind capacity outstrips the EU and they are past their tipping point, you want to see their crude inports. India is already on the path to green in a meaningful way. Today we have 43% from wind.
The anti green power lobby keep falling over but people still follow them. Don’t know why.
The world has to start somewhere. We only have this planet and already more parts of it are becoming uninhabitable. Soon we will be at the poles. Try getting 8 billion folks on those tiny spaces.
Oh, and as the US self destruct on green energy, China is going for that market. That means US has chopped itself out of a market it could have had a massive input to because anti green idiot is in the Whitehouse and China could take control. And if we are unlucky, we get a mini Trump in No10. Guess what that will cost us?
Excellent article! Mid Wales is seeing three large developments each of around 1,000 MW, yet each one has been divided up into multiple smaller wind farms and separate grid connections, each of which is being pushed through separately Prior to onshore wind being devolved to the Senedd, these would have been consented as three integrated wind farms under the Planning Act 2008, which is still used for offshore wind farms. Now they are being pushed through the Town and Country Planning Act All three of these, the total 3,000 MW, will still only produce a similar output as the single… Read more »
The use of the word ‘industrial park’ makes me think of industrial estates… and in no way does a wind farm look like an industrial estate.